Removing a wall that truly carries no load is usually one of the simpler interior tear-outs. The price and the risk both depend on what you confirm first. Junk 'Of' Urs does not decide whether a wall is load-bearing. A structural engineer or a qualified general contractor confirms that before anything comes down. This page is not engineering advice, and it is not legal advice.

Homeowners in Toronto, York, and Durham use this for an open-concept change once the partition is confirmed non-load-bearing. Contractors and project managers use it when that wall should come out and leave in one visit. The permit question is at junkofurs.com/blog/interior-demolition-permit-toronto. What a selective interior tear-out means is at junkofurs.com/blog/what-is-selective-demolition. Kitchen and basement prices are separate guides, at junkofurs.com/blog/kitchen-demolition-cost-toronto and junkofurs.com/blog/cost-to-gut-a-basement-toronto.

Confirm the wall carries no load

A few clues show up in almost every open-concept plan. Joists that run into the wall, rather than parallel to it, are one hint. A wall that sits on a beam, or that stacks over a wall on the floor below, is another. Exterior walls, and walls near the middle of the house, are hints too. Treat every one of those as a hint only. None of them settles the question.

A structural engineer or a qualified general contractor should confirm the wall before anything comes down. Put that confirmation in writing, and keep it with the photos you send us. We do not judge whether a wall is load-bearing. Load-bearing walls, beams, posts, and any structural work are outside our scope. We do not remove load-bearing walls. If that confirmation is not in hand, the wall stays.

What is inside the wall

A partition wall often hides more than studs. Outlets, switches, plumbing, a gas line, or an HVAC duct can run through it. Those systems have to be shut off, and moved or capped, by the right trade before tear-out starts. An electrician handles the wiring. A plumber handles the water lines. The right trade handles gas and the ducts. We do not do electrical, plumbing, gas, or HVAC work.

Say what is visible in the wall, and who has already made it safe. If a trade still has to move a line, book that visit first. We arrive after the wall is safe to open.

Permits, condos, and your municipality

Removing a wall that changes room sizes or uses, or that alters plumbing, can need a building permit. Confirm that with Toronto Building or your contractor before work starts. The short version, and the City's own lists, are in the interior demolition permit guide at junkofurs.com/blog/interior-demolition-permit-toronto. Start at the City of Toronto building permit page: https://www.toronto.ca/services-payments/building-construction/building-permit/. If that page and this guide ever differ, follow the City. This page does not quote a fee or a timeline. It is not legal advice.

Outside Toronto, check the local building department for the address. That includes municipalities in York and Durham, such as Vaughan, Markham, Richmond Hill, Pickering, Ajax, Whitby, and Oshawa. This guide does not state their rules. Our crew still serves Toronto, York, and Durham once the approvals for that address are clear.

A condo or apartment usually also needs management approval, set work hours, and a booked service elevator. Get those rules in writing before you book a crew. Elevator windows, padding, and hours are covered at junkofurs.com/blog/condo-renovation-demolition-toronto.

Older plaster and suspect finishes

In older homes, plaster, joint compound, and some textured finishes can contain asbestos. Health Canada says that before 1990, asbestos was mainly used to insulate buildings and homes and to fireproof them. Health Canada also says asbestos may still be found in older building materials, including cement and plaster, and in surface treatments such as drywall, paint, and spackling. Dust from drilling, sanding, breaking, or removing those materials is how fibres get into the air.

Have suspect material tested by a qualified professional before the wall is opened. Health Canada says to hire a professional to test before renovating or remodelling, and, if asbestos is found, to hire a qualified asbestos removal specialist. Junk 'Of' Urs does not test for, handle, or remove asbestos or any hazardous material. Work stops until that is cleared. The page to read is Health Canada's Asbestos and your health: https://www.canada.ca/en/health-canada/services/air-quality/indoor-air-contaminants/health-risks-asbestos.html.

Plaster on wood lath is heavier and dustier than a drywall partition. Weight, dust, and how that haul is priced are in the lath and plaster guide at junkofurs.com/blog/lath-and-plaster-removal-toronto. Drywall that is already down is a different guide, at junkofurs.com/blog/drywall-disposal-toronto.

What the visit includes, and what it costs

Once the wall is confirmed non-load-bearing, the services are safe, and the approvals are clear, a typical non-structural tear-out is straightforward. We protect the floors and close off the room. How to protect floors before a haul is at junkofurs.com/blog/protect-floors-before-junk-removal. We remove the trim, then the drywall or the plaster. After the trades have made the services safe, we remove the studs and the plates. We bag the debris and carry it to the truck. We leave the opening ready for the drywall and flooring trades to patch. Patching the floor, the ceiling, and the neighbouring walls is a separate trade job after we leave, unless your contractor is handling that finish work.

For contractors and project managers, that is the point of one visit. Partition walls come out and the debris leaves with us, so the next trades walk into a ready site. We're not a junk company. We're your site-clearing crew. Stop renting a bin. Hire a crew. How a crew compares with a bin, with no bin prices, is at junkofurs.com/blog/junk-removal-vs-bin-rental-toronto. What the interior tear-out service includes is at junkofurs.com/services/selective-demolition. Debris that is already down is at junkofurs.com/services/demolition-debris-removal. Leftovers from a renovation that is already open are at junkofurs.com/services/renovation-debris-removal.

Every figure below is before HST. HST is extra. There is no package price, no price per wall, and no price per square foot. We do not guess how many loads one wall makes. A single partition wall is often a small share of a load. Photos let us give a written range before anyone books. Junk and debris are priced by how much of the truck the pile fills, not by the hour. The hourly rate is only for tear-out labour.

Light mixed renovation and demolition debris, before HST, is a small pile at $99 to $150, an eighth of a load at $150 to $220, a quarter at $250 to $400, a half at $400 to $550, three quarters at $550 to $700, and a full load of about 15 cubic yards at $650 to $850. Each full load includes 60 to 90 minutes of loading and tear-out time.

Tear-out labour after that included time is $100 to $150 per hour for a two-person crew. The work stays interior and non-structural.

Plaster and lath in bulk, and other dense material, use the heavy schedule. A heavy call-out is $300 to $450, then about $100 to $160 per tonne after the allowance. If the load weighs more than the photos suggested, we re-quote from the scale ticket.

Stairs, a basement, or a long carry to the truck add $50 to $150 or more. Debris that is already curbside-ready can take 5 to 15 percent off the haul when that discount applies.

Photos that get a written price

For a fast quote, send a wide shot of the wall from both sides. Add close-ups of any outlets, switches, vents, or pipes in it. Note whether the wall is drywall or plaster, and photograph the floor and the ceiling where the wall meets them. Include the stairs and the exit path, and the driveway or curb where the truck can sit. Add a note on who confirmed the wall is non-load-bearing, and whether suspect material has been tested.

We confirm volume, access, and weight from those photos, then in writing, before anything is removed. Send them for a written price at https://junkofurs.com/quote. Great projects start with a clean slate.

Frequently asked questions

How much does it cost to remove a non-load-bearing wall?
There is no per-wall price. Before HST, a light mixed haul is a small pile at $99 to $150, an eighth at $150 to $220, a quarter at $250 to $400, a half at $400 to $550, three quarters at $550 to $700, and a full load of about 15 cubic yards at $650 to $850. Each full load includes 60 to 90 minutes of loading and tear-out time. Tear-out labour after that is $100 to $150 per hour for a two-person crew. Plaster in bulk starts at $300 to $450, then about $100 to $160 per tonne. Stairs or a long carry add $50 to $150 or more. A single partition is often a small share of a load. Photos give the written range.
Can you tell me if my wall is load-bearing?
No. Joist direction, a wall over a beam, a wall stacked over a wall below, an exterior wall, and a wall in the middle of the house are hints only. A structural engineer or a qualified general contractor should confirm the wall before anything comes down. We do not judge whether a wall is load-bearing, and we do not remove load-bearing walls, beams, or posts. This is not engineering advice.
Do I need a permit to remove an interior wall in Toronto?
Removing a wall that changes room sizes or uses, or that alters plumbing, can need a building permit. Confirm with Toronto Building or your contractor before work starts. The City's lists are in the interior demolition permit guide. Outside Toronto, check the local York or Durham building department. Condos usually also need management approval, set work hours, and a booked service elevator. This is general information, not legal advice.
What if the wall has wiring, plumbing, or a duct?
Those systems have to be shut off and moved or capped by the right trade before we open the wall. We do not do electrical, plumbing, gas, or HVAC work. Book that trade first, then send photos that show the wall is safe to take down.
What if the plaster might contain asbestos?
Stop and have it tested before the wall is opened. In older homes, plaster, joint compound, and some textured finishes can contain asbestos. Health Canada says to hire a professional to test before renovating, and to hire a qualified asbestos removal specialist if asbestos is found. We do not test for, handle, or remove asbestos or any hazardous material.

Soft-strip, demo and junk removal